- I-294 Tollway Ramps at Cork/88th Avenue Phase II Engineering: The Southwest Conference of Mayors have approved $2,000,000.00 for Phase II Design Engineering for the current Justice Tollway Ramp project through the Surface Transportation Program. The Village has selected Chris Burke Engineering to perform the Phase II Design Engineering. The Phase II Design Engineering kicked-off in April of 2019 and is anticipated to take approximately two years.
- I-294 Tollway Ramps at Cork/88th Avenue ROW/Land Acquisition: The Village of Justice has been awarded $1,443,680 million dollars through the Illinois Competitive Freight Program to assist with R.O.W land acquisition for the Justice I-294 Tollway Ramp Project. In addition, Cook County has awarded the village an additional $360,920 to cover the local matching funds. Cook County will lead the ROW/Land Acquisition portion of the project.
- I-294 Tollway Ramps at Cork/88th Avenue Phase III: The Village of Justice has been awarded $12,000,000 dollars through the Illinois Competitive Freight Program to help fund the construction of the project. The village anticipates a letting of early 2023.
- Illinois Jobs Now Program: This project is being completed in two separate phases. The first phase has been completed and included the reconstruction of 85th Ave and 85th Court from 79th Street to the Tollway; 86th Ave from 71st Street to 75th Street, and 73rd Place from Cork Ave to 86th Ave. The second phase of the project will include the reconstruction of the intersection at 75th Street, 86th Avenue and Archer Road. This project is being funded by the Illinois Department of Transportations Illinois Jobs Now Program in the amount of 2.6 million dollars. Phase II construction of this project is anticipated to begin in 2020.
- 2020 Community Development Block Grant Project: The Village of Justice was awarded $110,000 from Cook County through the 2020 Community Development Block Grant Program for the reconstruction of 82nd Street from 82nd Avenue to 83rd Avenue. Construction has started and this project will be completed in 2021.
- 2021 Community Development Block Grant Project: The Village of Justice was awarded $200,000 from Cook County through the 2021 Community Development Block Grant Program for the reconstruction of 83rd Street from 88th Avenue to 85th Court. The Village is currently waiting for a letter to proceed with construction and anticipate completing this project in 2022.
- 2020 Invest in Cook Grant Project: The Village of Justice was awarded $400,000.00 through the 2020 Invest in Cook Program to reconstruction 82nd Place from 88th Avenue going east to the end of the cul-de-sac. Construction is to begin in late 2021.
-
-
- 2021 Invest in Cook Grant Project: The Village of Justice was awarded $192,890.00 through the 2021 Invest in Cook Grant Program for the reconstruction of 86th Court from 83rd Street to the tollway. The Village is currently waiting for a letter to proceed with construction and anticipate completing the this project in 2022.
|